Developing a GIS-based MINLP framework for optimizing the waste-to-energy supply chain with plant scale considerations

Mashum Billal, Roshni Mary Sebastian, Amit Kumar

2025Journal of Cleaner Production10 citationsDOIOpen Access PDF

Abstract

Municipal solid waste (MSW) can be used to reduce reliance on fossil fuels and help transition towards a circular economy. The MSW supply chain is complex and needs to be optimized to minimize total supply chain costs. There are few studies on the integrated optimization of the MSW supply chain with a waste-to-energy (WtE) conversion facility. This study develops a framework to optimize various cost parameters, including feedstock collection, transportation, capital, maintenance, and operations costs simultaneously through an integrated GIS-based mixed-integer nonlinear programming (MINLP) model considering the WtE conversion facility scale. A GIS location-allocation analysis using the fuzzy analytic hierarchy process (FAHP) approach was used to identify candidate sites for WtE facilities based on environmental, economic, and social criteria. GIS origin-destination cost functions were used to determine the precise distances from transfer stations by road and rail to candidate facilities and subsequently landfills. These outputs were then used for the MINLP framework to optimize the number, location, and size of WtE facilities. A case study for Western Canada was conducted considering 447 landfills in 4 provinces. More than 5800 candidate locations and 598 transfer stations were screened. The results show that at a discount rate of 10%, the electricity production cost is competitive at only 10.99 $/MWh when the gate fee (charged by a WtE facility for processing waste) of 35 $/tonne and a carbon credit of 15 $/tonne are considered as a source of revenue, accounting for all cost factors. The optimal site is in Foothills County, Alberta, and it has a size of 183 MW. The sensitivity analysis shows the most sensitive parameters on the per-unit electricity production cost are plant efficiency, capital cost, and gate fees. The associated uncertainties in the cost of electricity production are 10.99±6.88 $/MWh. The results of the study can help in making investment decisions and policy formulation. • An integrated GIS-based MINLP model is developed for the biomass supply chain • Framework includes plant scales, actual biomass collection points and distances • The optimal plant site is in Foothills County, Alberta, Canada, at a size of 183 MW • The electricity production cost is competitive at only 10.99±6.88 $/MWh • Key sensitivity parameters are plant efficiency, capital cost, and gate fee on EPCs

Topics & Concepts

Scale (ratio)Waste-to-energyEnvironmental scienceEnergy (signal processing)Waste managementEngineeringCivil engineeringEnvironmental economicsMunicipal solid wasteComputer scienceEnvironmental engineeringGeographyMathematicsCartographyEconomicsStatisticsMunicipal Solid Waste ManagementRecycling and Waste Management TechniquesAdvanced Manufacturing and Logistics Optimization
Developing a GIS-based MINLP framework for optimizing the waste-to-energy supply chain with plant scale considerations | Litcius