Simulation of a Dubai based 200 KW power plant using PVsyst Software
M. Venkata Satish, Sharon Santhosh, Apurv Yadav
Abstract
With the exhaustion of fossil fuels, their dreadful effect on the environment and their soaring prices, renewable forms of energy like solar and wind power have emerged rapidly, as clean and sustainable sources of generating electricity. This paper studies the viability of deploying a 200 kWp on-grid monocrystalline silicon solar plant, by making use of PVsyst software for Dubai international academic city, Dubai. The system was designed to have 22 modules in series with 32 strings in parallel. And the total number of modules is computed as 704. The reports of the simulation were examined to determine the total production of energy and specific energy production which was found to be 352.6 MWh/year and 1757 kWh/kWp/year respectively. The annual performance ratio of the system was calculated as 81.67 %. Lastly, by identifying the main source of losses, the detailed loss for the entire year is estimated and represented by an arrow loss diagram.